Home Business  FG to Break Ground on Apapa and Tin Can Island Port Upgrades on November 25 Under £746m UK-Backed Financing

 FG to Break Ground on Apapa and Tin Can Island Port Upgrades on November 25 Under £746m UK-Backed Financing

by Radarr Africa Business Desk

LAGOS, November 18 (Radarr Africa) – The federal government will break ground on the modernisation of the Lagos Port Complex in Apapa and the Tin Can Island Port Complex on Wednesday, November 25, 2026, the Ministry of Marine and Blue Economy has announced.

Adegboyega Oyetola, the Minister of Marine and Blue Economy, will lead the ceremony, according to a statement issued by the ministry’s spokesperson on Monday, November 16. The ministry described the event as a groundbreaking ceremony and official turning of the soil for the two projects.

The works are backed by a £746 million (about N1.3 trillion) financing agreement with the United Kingdom, signed in March 2026. Citibank facilitated the deal. At least £236 million in supplier contracts is expected to go to UK firms, including a £70 million contract for British Steel to supply 120,000 tonnes of steel billets. The contract is British Steel’s largest export deal backed by UK Export Finance.

Nigerian Ports Authority (NPA) sources said the federal government had to meet its counterpart funding commitments before construction could begin in full. The first phase has since received Federal Executive Council approval for disbursement by the Central Bank of Nigeria, although the amount has not been disclosed.

Construction documents from the contractor, ITB Nigeria, show that the scope covers rehabilitation of bollards, safety ladders and apron slabs, along with structural works to support modern ship-to-shore gantry cranes. The works are meant to improve berthing and cargo-handling capacity, shorten vessel and cargo dwell times and reduce demurrage and logistics costs.

Apapa port was commissioned in 1926, while Tin Can Island port began operations in 1977. Together the two ports handle more than 85 per cent of Nigeria’s container trade, according to the National Bureau of Statistics.

NPA figures for the first half of 2026 point to the strain on the ports. At Apapa, average vessel turnaround time rose from 5.9 days to 6.1 days. At Tin Can Island, vessel calls fell 3.4 per cent to 488 from 505 in the first half of 2025, and turnaround time rose from 4.4 days to 5.1 days. By comparison, Tema port in Ghana averages three to four days, the NPA data show.

The ministry did not give a completion date for the first phase in its statement.

You may also like