NAIROBI, November 23 (Radarr Africa) – Kenya has started drilling in the South Lokichar Basin in Turkana County, a step towards commercial crude oil production that the government has targeted for December 1, 2026.
Energy and Petroleum Cabinet Secretary Opiyo Wandayi presided over the spudding ceremony at the Amosing 1 well pad on Friday, November 20. He called the event “a historical milestone ahead of first oil production”. Spudding is the start of drilling operations on a well, and it marks the first phase of Gulf Energy E&P BV SEZ’s development of the fields in Blocks T6 and T7.
Wandayi said he was impressed by the professionalism and commitment of Gulf Energy and its contractors in meeting the targets in the development plan. Gulf Energy is the government’s contractor for the project. He said the government was backing accelerated development of the fields in line with the Field Development Plan ratified by Parliament.
Paul Limoh, managing director of Gulf Energy, said the company was “maintaining a tight delivery and project management schedule”. He said the company is targeting six discoveries across Blocks T6 and T7, with an estimated recoverable resource of 326 million stock-tank barrels over a 25-year contract period.
The first phase covers the Ngamia, Amosing, Twiga and Ekales fields, known together as NEAT. Initial production capacity is expected to exceed 20,000 barrels per day, rising to 50,000 barrels per day in a second phase.
From December 1, the first crude will be trucked by road from Turkana to Mombasa, where it will be stored at the tank farms of Kenya Petroleum Refineries Limited.
The crude is light to medium, sweet and paraffinic, with an API gravity of about 30.5 degrees. Its high wax content affects handling and transport below the wax appearance point, which matters for a route that relies on road tankers. The oil is expected to be priced against Dated Brent.
The spudding followed the rigging, levelling and commissioning of the GW70 onshore drilling rig, which is leased from Great Wall Drilling Company of China. Baker Hughes will provide integrated well services, and SLB will deliver the Early Production Facility.
Roads and Transport Cabinet Secretary Davis Chirchir said the government is investing more than Sh24 billion, about $184.6 million, in infrastructure in the oil region, including roads. East African Community Cabinet Secretary Beatrice Askul also attended the ceremony.
The project is governed by production sharing contracts between Gulf Energy and the national government, with oversight from the State Department for Petroleum and the Energy and Petroleum Regulatory Authority. Government projections put lifetime earnings from the project at more than $2.9 billion, about Sh371 billion, depending on oil prices and actual output.